Scaffolding questions and answers

The basic scaffolding questions that come up in every interview, site test and toolbox talk, answered in one line each with the number and the document it comes from. Then test yourself with a free timed exam.

13questions
Freepractice exam
Withreferences

Technical questions

Q1What is a standard, a ledger and a transom?
  1. Three names for the same tube
  2. Standard: upright; ledger: horizontal along the scaffold; transom: horizontal across it, carrying the boards
  3. Standard: brace; ledger: tie; transom: base plate
  4. Standard: board; ledger: toe board; transom: guardrail

Answer: Standard: upright; ledger: horizontal along the scaffold; transom: horizontal across it, carrying the boards. Standards are the uprights, ledgers run along the face, transoms span across and support the boards. See the scaffold glossary.

More: Scaffold glossary.

Q2What is the size and weight of a standard steel scaffold tube?
  1. 42 mm × 3.2 mm, 2.5 kg/m
  2. 48.3 mm outside diameter × 4.0 mm wall, about 4.4 kg/m
  3. 60.3 mm × 5 mm, 7 kg/m
  4. 48.3 mm × 2 mm, 1.5 kg/m

Answer: 48.3 mm outside diameter × 4.0 mm wall, about 4.4 kg/m. 48.3 mm × 4.0 mm, about 4.37 kg per metre, so a 6.3 m tube is about 28 kg. BS EN 39 tube; see the free weight calculator. Verify against the latest edition.

More: Scaffold calculators.

Q3Which coupler joins two tubes at 90° and carries load?
  1. Swivel coupler
  2. Right-angle (double) coupler
  3. Putlog coupler
  4. Sleeve coupler

Answer: Right-angle (double) coupler. Right-angle couplers are the load-bearing 90° joints; swivels join at any angle (bracing), putlog couplers hold putlogs and transoms, sleeves join tubes end to end. BS EN 74-1. Verify against the latest edition.

From the free Scaffold Supervisor (EN/TG20).

Q4What do green, yellow and red scaffold tags mean on most Gulf sites?
  1. Green: safe to use; yellow: use only with the limits on the tag; red: do not use
  2. Green: being built; yellow: safe; red: inspected
  3. All three mean safe
  4. Colours have no meaning

Answer: Green: safe to use; yellow: use only with the limits on the tag; red: do not use. Green: inspected and safe within its limits. Yellow: limits apply, such as a harness. Red, an expired tag or no tag: do not use. GI 8.001 (2025) §9 on GCC oil and gas sites. Verify against the latest edition.

More: Tag colours.

Q5How high must the top guardrail be?
  1. It depends on the rules: OSHA 38–45 in, UK at least 950 mm, CSM II-2 0.95–1.15 m
  2. Always 1.5 m
  3. Always 0.8 m
  4. Any height above the toe board

Answer: It depends on the rules: OSHA 38–45 in, UK at least 950 mm, CSM II-2 0.95–1.15 m. 29 CFR 1926.451(g)(4); UK Work at Height Regulations 2005 Schedule 2; CSM II-2 §2.5.4. Full comparison on the guardrail height page. Verify against the latest edition.

More: Guardrail height compared.

Q6What is the usual maximum spacing of ties on a scaffold under the CSM?
  1. 4 m vertical, 4 m horizontal
  2. 8 m vertical, 9 m horizontal
  3. 12 m vertical, 12 m horizontal
  4. No ties needed under 20 m

Answer: 8 m vertical, 9 m horizontal. 8 m vertically (every 4 lifts or less) and 9 m horizontally. CSM II-2 §2.5.8; other rules differ, see the tie spacing comparison. Verify against the latest edition.

More: Tie spacing compared.

Q7How tall may a freestanding tower be compared with its smallest base?
  1. Stationary 4 ×, mobile on casters 3 ×
  2. Stationary 6 ×, mobile 5 ×
  3. Any height if tied
  4. 2 × for both

Answer: Stationary 4 ×, mobile on casters 3 ×. The 4:1 rule for stationary towers and 3:1 for mobile towers on casters, unless tied or the design allows more. CSM II-2 §2.9.1. Verify against the latest edition.

From the free Scaffold Inspector.

Q8What are the BS EN 12811-1 load classes for working platforms?
  1. Classes 1 to 6: 0.75, 1.5, 2.0, 3.0, 4.5 and 6.0 kN/m²
  2. Light and heavy only
  3. 1 to 3: 1, 2 and 3 kN/m²
  4. Every platform is 5 kN/m²

Answer: Classes 1 to 6: 0.75, 1.5, 2.0, 3.0, 4.5 and 6.0 kN/m². Class 1 is inspection only (0.75 kN/m²) and class 6 is heavy masonry storage (6.0 kN/m²). The CSM uses light, medium and heavy duty ratings in CSM II-2. See the load classes page. Verify against the latest edition.

More: Load classes compared.

Q9How often must a scaffold be inspected?
  1. OSHA before each shift; UK at least every 7 days and after changes or bad weather; CSM tags at most every 2 weeks
  2. Once a year
  3. Only at handover
  4. Every 90 days

Answer: OSHA before each shift; UK at least every 7 days and after changes or bad weather; CSM tags at most every 2 weeks. 29 CFR 1926.451(f)(3); UK Work at Height Regulations 2005 Schedule 7; GI 8.001 (2025). Verify against the latest edition.

More: Inspection frequency compared.

Q10Who may alter a scaffold, for example remove a guardrail or move a tie?
  1. Any trade that needs to
  2. Only authorised scaffolders, then the scaffold is inspected and tagged again
  3. The user's foreman
  4. Anyone with a permit

Answer: Only authorised scaffolders, then the scaffold is inspected and tagged again. Only the scaffold crew changes a scaffold; after any change it is re-inspected before use. GI 8.001; NASC TG20:21. Record tie moves with the free tie move record. Verify against the latest edition.

More: Tie move record.

Questions you answer out loud

Q11What is the difference between tube and fitting and a system scaffold?

A strong answer covers:

  • Tube and fitting: loose tubes joined with couplers, any shape, slower, needs skill.
  • System (Ringlock, Cuplok, frames): fixed node points and set lengths, faster and repeatable, fewer shapes.
  • Design rules: TG20:21 for tube and fitting, TG30:24 and the maker's data for system scaffolds in UK practice.
Q12Walk me through the parts of an independent tied scaffold from the ground up.

A strong answer covers:

  • Sole boards and base plates, standards, ledgers and transoms.
  • Bracing (ledger and face bracing), ties into the structure.
  • Boards, guardrails, toe boards, access, and the tag.

Tip: Name them in the order you build them.

Q13When do you stop work on a scaffold?

A strong answer covers:

  • No tag, a red or expired tag, or a missing part (tie, guardrail, board).
  • Wind over the site limit, lightning, sandstorm.
  • Any change you did not expect: then report it and wait for inspection.

Technical answers are written by AL-YASSIN from its question banks, with the document each one is based on; verify against the latest edition and the rules of the project you are applying to. Scenario answers are practice guidance, not a script. AL-YASSIN is an independent company with no external accreditation.

Hiring? Check before the interview

Ask candidates for their AL-YASSIN certificate number and check it in seconds, or send a free screening link to a shortlist.

More

Questions

What are the main parts of a scaffold?

Sole boards and base plates, standards (uprights), ledgers (along), transoms (across), braces, ties, couplers, boards, guardrails, toe boards and access ladders or stairs.

What does a red scaffold tag mean?

Do not use: the scaffold is unsafe or not finished. On GCC oil and gas sites an expired tag counts as red (GI 8.001 (2025) §9). Verify against the latest edition.

Where can I test my scaffolding knowledge for free?

AL-YASSIN has free timed scaffold exams with certificates anyone can verify online: Scaffolder Level 1, scaffold practice exams, OSHA and BS EN 12811-1 / TG20 supervisor exams and role exams.