Technical questions
Q1Under CSM II-2, what is the smallest base plate allowed under every scaffold post?
- 100 × 100 mm, 4 mm thick
- 150 × 150 mm, 6 mm thick
- 200 × 200 mm, 8 mm thick
- 150 × 150 mm, 3 mm thick
Answer: 150 × 150 mm, 6 mm thick. Base plate at least 150 × 150 mm and 6 mm thick under every post, on a timber sill at least 225 mm wide and 38 mm thick. CSM II-2 §2.5.2. Verify against the latest edition.
From the free Saudi Aramco Scaffold Supervisor I exam.
Q2A green tag on a scaffold has passed its date. What is the scaffold's status?
- Green until the next inspection
- Yellow: harness users only
- Red: no work until a new signed tag
- Green if the supervisor says so
Answer: Red: no work until a new signed tag. An expired tag counts as red: no work until a new signed tag is in place. GI 8.001 (2025) §9. Verify against the latest edition.
From the free Saudi Aramco Scaffold Supervisor I exam.
Q3How far may a screwjack be extended?
- Half the threaded length
- Two thirds of the threaded length
- The full thread
- As far as the base plate allows
Answer: Two thirds of the threaded length. Maximum screwjack extension is 2/3 of the threaded length. Level with the jack, never with bricks or packing. CSM II-2 §2.5.2. Verify against the latest edition.
From the free Saudi Aramco Scaffold Supervisor II-T exam.
Q4What is the minimum timber sill under base plates?
- 150 mm wide × 25 mm thick
- 200 mm wide × 32 mm thick
- 225 mm wide × 38 mm thick
- 300 mm wide × 50 mm thick
Answer: 225 mm wide × 38 mm thick. Timber sill at least 225 mm wide and 38 mm thick, under at least 2 posts, on sound, compacted, level ground. CSM II-2 §2.5.2. Verify against the latest edition.
From the free Saudi Aramco Scaffold Supervisor II-S exam.
Q5At what wind speed must all use of a scaffold stop?
- 30 km/h
- 37 km/h
- 40 km/h
- 50 km/h
Answer: 40 km/h. Stop erection at 37 km/h; stop all use at 40 km/h and re-inspect before restart. CSM II-2 Table 2.3. Verify against the latest edition.
From the free Saudi Aramco Scaffold Supervisor II-S exam.
Q6A ladder gives access to a platform. How far must its top extend above the landing?
- 0.5 m
- 1 m
- 1.5 m
- 2 m
Answer: 1 m. Ladder top at least 1 m above the landing, set at 4 : 1 and tied off at the uppermost support. CSM II-3 §3.4. Verify against the latest edition.
From the free Saudi Aramco Scaffold Supervisor II-T exam.
Q7Four boards are checked against their described lengths. Which one is outside the BS 2482 length tolerance?
- 2.40 m board measuring 2.42 m
- 3.00 m board measuring 2.97 m
- 3.90 m board measuring 3.88 m
- 4.20 m board measuring 4.16 m
Answer: 3.00 m board measuring 2.97 m. Length tolerance is ± 25 mm, or ± 50 mm for boards longer than 3.9 m. The 3.00 m board is 30 mm short, outside ± 25 mm. The 4.20 m board is 40 mm short but within ± 50 mm; the 3.90 m (−20 mm) and 2.40 m (+20 mm) boards are within ± 25 mm. BS 2482:2009 5. Verify against the latest edition.
From the free Scaffold Supervisor (BS EN 12811-1 and TG20) exam.
Q8Which of these platforms meets the minimum width in 1926.451(b)(2)?
- Ladder jack scaffold: one 2×12 plank, 11-1/4 in wide
- Pump jack scaffold: two 2×8 planks, 7-1/4 in each
- Frame scaffold: two fabricated planks, 8 in each
- Top plate bracket scaffold: one 2×10 plank, 9-1/4 in wide
Answer: Pump jack scaffold: two 2×8 planks, 7-1/4 in each. The general minimum is 18 in; ladder jack, top plate bracket and pump jack scaffolds may be 12 in. Pump jack: 2 × 7.25 = 14.5 in ≥ 12 in. The ladder jack (11.25 in) and top plate bracket (9.25 in) platforms are under 12 in; the frame scaffold's 16 in is under 18 in. Nominal lumber sizes overstate actual widths. 29 CFR 1926.451(b)(2), (b)(2)(i). Verify against the latest edition.
From the free US Scaffold Supervisor (OSHA 1926) exam.
Site scenarios
Q9Your crew is ready at 06:00 but the work permit is not signed. What do you do?
A strong answer covers:
- No erection starts without the permit, however long the queue.
- Use the wait: toolbox talk, material check against the drawing, barricades and exclusion zone ready.
- Chase the permit issuer and tell your superintendent the time you are losing.
- Write the delay in the daily report with the start and end time.
Tip: The written delay record is what later supports a standby or extension claim.
Q10The wind picks up while the scaffold is half built. What do you do?
A strong answer covers:
- Stop at a safe stage: no loose boards or tubes left at height, everything tied in or lowered.
- Tag it as not for use and barricade it.
- Follow the site wind limits (for example, on Saudi Aramco sites erection stops at a lower speed than use does).
- Inspect again before anyone goes back up.
Q11A user has taken out a guardrail to pass materials up. How do you handle it?
A strong answer covers:
- Stop the work and make the edge safe first.
- Only scaffolders, under a competent person, alter a scaffold; the tag status changes until it is inspected again.
- Report it and brief the user's supervisor.
- Fix the cause: plan a loading point or a gate so nobody needs to remove a rail.
Q12You are short of ties and couplers to finish. Do you hand over the scaffold?
A strong answer covers:
- No. An incomplete scaffold is not handed over and never improvised.
- If part of it is complete and safe, hand over only that part, tagged, with the rest closed off.
- Order the shortage the same day and record it.
Q13Plan tomorrow for a crew of six.
A strong answer covers:
- Scope and drawing, quantities in m³, m² or lm, and the output you expect per productive scaffolder.
- Material on site checked against the list; lifting needs; access route.
- Permits and hold points: who inspects and signs before handover.
- In heat, heavy lifting early, water and rest breaks built into the plan.
Tip: Give a number. "Six men, one chargehand, about 22 m³ by the end of the shift" sounds like someone who has done it.
Q14How do you brief a crew that speaks four languages?
A strong answer covers:
- Short sentences and the site words everyone knows.
- Show it on the scaffold, do not only say it.
- Ask one person from each group to repeat the key point back.
- Use a bilingual chargehand and pictures for the rule of the day.
About you
Q15Tell me about a time you refused to hand over a scaffold.
A strong answer covers:
- What was missing and why it mattered.
- Who pushed back and how you explained it.
- How fast you closed it and what you changed afterwards.
Q16The client wants it faster than your crew can build it safely. What do you say?
A strong answer covers:
- Show the numbers: crew, output, hours.
- Offer real options: more men, a second shift, a staged handover.
- Never trade away a check or a tie to win time.
Q17What do you check before you sign a tag?
A strong answer covers:
- Foundation, plumb, bracing and ties against the design.
- Full boarding, guardrails, toe boards and access.
- Load class matches the job; the tag shows the right status and date.
Technical answers come from the AL-YASSIN question banks, with the document each one is based on; verify against the latest edition and the rules of the project you are applying to. Scenario answers are practice guidance, not a script. AL-YASSIN is independent and not endorsed by Saudi Aramco, OSHA, BSI or NASC.
How to answer the "tell me about a time" questions
Use four short parts: the situation (where, what scaffold, how high), the task (what you had to decide), the action (what you did, in order) and the result (what changed, with a number if you have one: days saved, findings closed, zero incidents on that job). Keep it under two minutes. Interviewers in this trade listen for one thing above all: that you stop the job when it is not safe, and then find a way to finish it.
Hiring? Check before the interview
Ask candidates for their AL-YASSIN certificate number and check it in seconds, or send a free screening link to a shortlist.
More
Questions
What questions are asked in a scaffold supervisor interview?
Expect three kinds: technical numbers (base plates, sills, screwjacks, ties, guardrail and toe board heights, wind limits, tag colours), site scenarios (permits, wind, missing materials, a user removing a guardrail) and questions about your own record, such as a time you refused to hand over a scaffold.
How do I prepare for a Saudi Aramco scaffold supervisor interview?
Know the scaffold rules of the Construction Safety Manual and GI 8.001 well enough to explain them on site, practise with timed questions, and prepare two or three short stories from your own jobs. The free AL-YASSIN practice exams are independent and are not a Saudi Aramco test.