Home/Most-missed questions/Sills: when a 765 mm sill under one post is allowed
Scaffold sills: when is a 765 mm sill under one post allowed?
The joint 4th most-missed question across our free scaffold practice exams. Read it, pick a letter, then open the answer.
Practise for the supervisor, inspector and rigger cards
Free timed exams that test real site knowledge. Certificate checked by QR.
The question
On level, compacted ground, a crew sets a separate 765 mm timber sill under each post of a scaffold. What is correct?
- Not compliant; single-post sills must each be at least 1,200 mm long
- Compliant, if each sill is at least 225 mm wide and 38 mm thick
- Not compliant; each sill must extend under at least two posts here
- Compliant; 765 mm is the minimum sill length under any post
Show the answer
Answer: C) Not compliant; each sill must extend under at least two posts here
Why: On level, compacted ground a sill must run under at least two posts.
Separate sills under single posts, each at least 765 mm long, are allowed only where two-post sills are not feasible because the ground is uneven or sloping.
So 765 mm is not a minimum for any post. It is the minimum for a single-post sill, and only on ground that forces one.
The trap: Options A, B and D all miss the two-post rule.
Reference: CSM II-2 §2.5.2 D. Verify against the latest edition.
Remember these 3
- 2 postswhat a sill runs under on level ground
- 765 mmthe minimum length of a single-post sill
- Uneven or sloping groundthe only reason to use one
How often it is missed
Wrong on 41 papers so far, the joint 4th most-missed question across our free practice exams; 31 of the 41 were Scaffold Supervisor I papers (data as of 6 Nov 2026).
Foundations questions scored 55% correct on Scaffold Supervisor I papers (229 of 416 answers, 208 papers, data as of 8 Nov 2026).
Counted on papers of 10 minutes or more, test entries removed.
Try 50 questions like this one
Free, timed, on your phone: 50 questions in 50 minutes, pass mark 85%. Pass and you get a certificate anyone can check by its QR code.
Words on this page
- Sill (sole board)
- the timber under the base plates that spreads the load into the ground
- Base plate
- the steel plate at the foot of each post
More most-missed questions
Reference: CSM II-2 §2.5.2 D. Verify against the latest edition.